Construction and Development Solutions was hired to manage the construction and assist in the design of a new crush facility and a 500,000 gallon tank farm. Working with StrataAP, (www.strataap.com) design work began in the spring and the entire project was completed before the fall crush.

The design / build team was asked to relocate an existing crush facility located in Napa. This required relocating two Bucher presses that were refurbished will new bladders and controls. The truck dock was transformed into a crush facility with a new motor control center, auger pit, and catwalk structure. Within the building, trench drains, tanks pads, must lines, glycol lines, catwalks and 500,000 gallon of tanks were installed.

CDS-Inc. coordinated all on-site activities, negotiated all contracts and managed the construction until final permits were obtained and the all systems were fully operational.